Completed Project
1.Dec 2012-Jan 2013 Piping Fabrication TTM Project Customer : TriAor Construction
2.Mar 2013-May 2013 TTS Workshop Fabrication Customer : TTS
3. Jan 2013-Dec 2013 Supply Manpower Customer : EGAT( Krabi Power Plant )
4.Dec 2013-Jan 2014 Maintenance Fire Truck Customer : Tranthai Malaysea (Thailand )Co,LTD
5.May 2014-June 2014 Repair&Refabrication carburator pipe spool : Saraff Biogas Energy Co,Ltd
6.Jan 2014-Aug 2014 TTS Office Building Customer : TTS
7.Jan 2014 - Dec 2014 Supply Manpower Customer : EGAT(Krabi Power Plant)
8.Feb 2014-Jan 2015 Piping Fabrication Ichthys OnShore LNG Facilities Project Customer : STP&I
9..March 2015-Aug 2015 Dryer system of Solar Energy : Department of Alternative Energy Development and Efficiency
10.July 2015-Aug 2015 Pipe Line Fabrication and Installation 350 m :TriAor Construction
11.Sep 2015-Oct 2015 Belt Convayer Fabrication : Sotus Engineering Co,LTD
12.Jan 2015-Jan 2016 Supply Manpower Customer : EGAT(Krabi Power Plant)
13.March 2015-Jan 2016 Welder Fitter and Worker Supply Manpower for Fabrication :EGAT(Krabi Power Plant)
14.Sep 2015- Jan 2016 Pipe Coating 1200 m : EGAT ( Krabi Power Plant )
15.Nov2015-Jan2016 Golf Net Couse Installation : Sofitel Luxury Hotel
16.Jan 2016-Mar 2016 Platfrom Installation PTT Site Customer : TriAor Construction Co,Ltd
17..May 2016-Present Organic vegetables Farm 20 Building : k.Korawan
18.Mar 2016-Present Dryer system of Solar Energy : Department of Alternative Energy Development and Efficience
19.July 2016-Aug 2016 Structure Fabrication and Installation Trans Thai Malaysia : TreAor Construction Co,LTD
20.Jan 2017-March 2017 Supply Manpower Customer : EGAT(Ratchaburi Power Plant)
21.Feb 2017-March 2017 Supply Manpower Customer : Sotus Engineering
22.July 2017-Aug 2017 Pipe Coating : EGAT(Krabi Power Plant)
23.May 2017-Oct 2017 Supply Manpower Maemoe EGAT Lampang : CD Co,LTD
24.Oct2017-Dec 2017 Stub Tube Boiler Repair RGC-C10,11 : EGAT(Rtchaburi Power Plant)
25.Jan2018-Feb2018 Repair GGH Casing : EGAT(Maemaoa Power Plant)
26.April2018-June2018 Structure Fabrication : STP&I Public Company Limited
27.Sep2018-Oct2018 Cooling and Sealing Air Pipe System : EGAT(SBK-C22)
28.Repair Handle Valve NGV Station Chana :PTT Public Company Limited
29.Under Ground Pipe ReCoating NGV Station Chana :PTT Public Company Limited
30.Repair Grating Krabi Power Plant : EGAT(Krabi Power Plant)
31.Sep2018-Oct2018 NGV Station Chana Pipe Vent Modification : PTT Public Company Limited
32.Oct2018-Nov2018 Water Wall Tube Maemao Power Plant : EGAT(MMP-T12)
33.Jan2019-Jan2019 Repair Valve and Preheater&PWHT Ratchaburi Power Plant : EGAT(RGC-C30)
34.June2019-Aug2019 Nitrogent injection System Modify Piping : PTT Public Company Limited
35.July2019-Sep2019 Water Wall Tube Maemao Power Plant : EGAT(MMP-T09)
36.Jan2019-Jan2019 Water Wall Tube Maemao Power Plant : EGAT(MMP-T08)
37.Sep2019-Nov2019 Repair LP OTC North Phranakornn Power Plant : EGAT(NBK0)
38.Jan2020-June2020 Fabrication Steel Structure Chunburi Plant : STP&I Public Company Limited
39.Aug2020-Oct2020 Modify Plate for DC-Decoupler PTT Chana Station : CGL Engineering
40.June2021-Aug2021 Repair Corrosion Vessel Receiving Chana Station: PTT Public Company Limited
41.June2021-Aug2021 Repair and Recoating Support Chana Receiving Station: PTT Public Company Limited
42.June2021-Aug2021 Repair Insulation Gasket Pipe System Chana Receiving Station: CGL Engineering